ZeroPoint deployed the first of its kind biomass gasification power plant in Bulgaria. The project developer was Bara Group Ltd., a fully owned subsidiary of CEZ, a. s. – one the largest utility companies in Central and Eastern Europe.

The project was a 4.5 MWe Combined Heat and Power plant using the ZeroPoint gasification technology and woodchips as a primary source. In 2014 Bara Group commenced the construction of the 1st phase from the Plant with capacity of 2 MWe using local EPC contractor and first-tier suppliers, among which ZeroPoint. The plant was successfully commissioned in Q4 2015.